Who Delivers What in a Web Design Project? The Responsibility Matrix

Talha Aslan 19 min read 4 views

Short answer

What is a responsibility matrix in a web design project, and who delivers what?

A responsibility matrix is a planning table that shows, for every work item in a web design project, who produces it, who approves it, and when it is due. The client side owns content, images, access, and approvals; the agency side owns design, development, testing, and launch. The matrix exposes the source of delays before the project starts.

Keep reading for the full details and examples

If you are about to request a proposal, your real worry probably sounds like this: what will land on my desk, and where will it get stuck? This article answers exactly that. First we explain the logic of the matrix. Then we walk through content, images, access, approvals, testing, and launch, naming who delivers what in each row. Talha Aslan and his team share this table with every proposal, because most delays grow out of the sentence "I thought you were doing that". At the end you will find a filled-in sample matrix you can adapt.

Why should the responsibility matrix exist before the project starts?

Preparing the matrix before kickoff is the only reliable way to cut delay sources before the schedule is even written. A matrix built mid-project, however, cannot recover weeks that are already gone. A matrix that appears at the proposal stage also shows that the agency truly knows the process.

Building it early, in practice, brings three concrete benefits.

  • You set a realistic schedule, because every deliverable has an owner and a date.
  • Reading the price becomes easier, so you can see whether copywriting or photography is in the quote.
  • Your own team gets warned in time; for example, accounting prepares billing details in week one, not week three.

These benefits make full sense alongside the contract. The matrix answers "who does it", while the contract answers "what happens if they don't". We covered the second half in what to include in a web design contract. A good matrix also feeds the project schedule directly. The schedule itself lives in how long it takes to build a website, so we will not repeat it here.

What is the difference between a responsibility matrix and a brief?

A brief describes what the website will be; a responsibility matrix describes who will deliver which piece, and when, to make that website real. In other words, the brief defines the goal and the matrix defines the work. Neither replaces the other; together, however, they complete the project plan.

In practice the difference looks like this. The brief says "the services page will list six services". The matrix says "six service descriptions, client produces, week 2, single document" and "service icons, agency produces, week 3". Without a brief the matrix stays empty, because you cannot know which tasks exist. Without a matrix the brief floats, because nobody knows who carries the goal. We explained brief preparation in how to write a website design brief; this article completes the "who" question that the brief leaves open.

Preparing both documents in the same meeting is the most efficient route. As you read each brief line, ask "who will deliver this", and the matrix writes itself. That way you collect the same information once, and the two documents never contradict each other.

Which roles appear in the matrix?

A classic responsibility matrix has four roles: producer, approver, consulted, and informed. The producer does the work, and the approver has the final say. The consulted party gives input, and the informed party simply stays in the loop. In a web project you distribute these roles between the client side and the agency side.

For small business projects, simplifying the roles works well. Three columns usually suffice, for example: client produces, agency produces, both decide together. Too many columns make the matrix hard to read, and then nobody looks at it. Still, every row needs exactly one approver; two approvers means zero approvers.

Example scenario: at a manufacturing company, the sales manager wrote the product descriptions. The general manager then approved them, and the agency placed them on the pages. Because the matrix row read "copy: client produces, client approves, agency implements", nobody ever asked who was writing the text. In the same company's earlier project without a matrix, the copy sat ownerless for three weeks.

Who is responsible for content, the client or the agency?

Content, meaning page copy, product descriptions, and the about page, belongs to the client unless the contract says otherwise. The agency supplies the structure, the heading hierarchy, and character limits. The business then writes the words itself or buys a separate copywriting service. Settling this at the proposal stage removes the most common cause of delay.

Why the most common? Because writing copy is the task that always sits under "tomorrow" on a business owner's calendar. Design finishes, development finishes, and still the copy has not arrived. So in the content row, write not only the owner but also the due date and the format: "page copy, client, business day 10, single document".

When you fill in the content row, list these sub-items separately.

  1. Page copy: home, services, about, contact.
  2. Legal text: privacy notice, cookie policy, terms of sale if you sell online.
  3. Blog or news content: how many posts at launch, and who writes them.
  4. Form text: thank-you message, error messages, automatic emails.

A note on legal text: this is not legal advice. Prepare those pages with your legal advisor; the agency only places them on the site. For the full list of material you will be asked to supply, see what to prepare before hiring a web designer.

Who supplies the images, and in what format?

Images, meaning the logo, product photos, team photos, and any video, are material the client supplies. The agency then processes, resizes, and places them. Stock image selection and icon design, on the other hand, usually stay on the agency side. Writing these two halves in separate rows ends the "where are the photos coming from" debate.

The delivery format matters as much as the owner, so the format column of the matrix proves especially useful here. We ask for the logo as a vector file and product photos in high resolution with a consistent background. A low-resolution photo breaks the design and, as a result, burns a revision round. Before sending, you can check dimensions and file weight with our image resizer. Still, keep the originals, because the agency will handle final compression itself.

Items that often go missing from the image row include the following.

  • Social sharing image: the cover shown when a link is shared.
  • Favicon: the small icon in the browser tab.
  • Client logos: do you have permission, and at what size?
  • Team photos: same lighting and same framing, or not?

Once these items are in the matrix, the agency reserves space in the design and you schedule the photo shoot in time. If photography is not in the quote, it becomes a hidden line item; we compare quotes that differ this way in why web design quotes differ so much.

Who provides access credentials, and when are they needed?

Access credentials, meaning the domain registrar, the hosting account, the current site admin, and analytics logins, come from the client. The agency needs them in the first week. The agency cannot prepare the launch without them, so this row comes first. For that reason the access row is one of the earliest dated rows in the matrix.

The common problem with access, in practice, is not knowing who holds it. An acquaintance registered the domain years ago, hosting sits with another company, and the previous agency never handed over the password. Solve this in week one; otherwise launch day brings surprises. You can see which server your domain points to with our dns lookup tool, so you and the agency look at the same picture.

For security, never send credentials in the body of an email, because inboxes change hands and old messages linger for years. A password manager share or the agency's secure form is the better route. Also, narrowing or removing the agency's access after the project is your right; write that into the "post-launch" row of the matrix.

Who gives approvals, and what happens when approval is late?

Approvals always sit on the client side; however, writing "client" in the matrix is not enough. You need the name and the authority of the person who approves. When the approver is unclear, deliverables wait in limbo and, as a result, the project stalls. That makes the approval row the most critical row in the whole responsibility matrix.

The approval row has four gates: brief and sitemap, design, development, launch. Each gate also needs a duration, for example "design approval, general manager, 3 business days". State what happens when the window expires too: does the schedule shift, or does the deliverable count as approved? Think about this together with design feedback rounds; we covered round counts and batched feedback in revision rounds in a web design project.

Example scenario: at a three-partner company the matrix said "approval: partners". Each partner looked on a different day, left different notes, and design approval took five weeks. In the next project the row read "approval: marketing lead, consults partners, 3 business days", and the same stage closed in one week. The difference was not in the design; it was in the matrix.

What do design and development cover on the agency side?

On the agency side, the matrix covers design, development, technical setup, and measurement infrastructure. The design row includes homepage and inner page templates in desktop and mobile views. Development, in turn, covers coding the theme, setting up the admin panel, making forms work, and performance tuning.

The detail most often skipped in these rows is "admin training" and "content entry". Who enters the content into the site? You wrote the copy, but who uploads it into the panel? If the matrix does not say, the agency says "we placed it" and you say "half of it is missing". For what to expect from the admin panel and the handover, see website handover checklist.

Using measurable criteria in the agency rows reduces arguments. For example, write Google's Web Vitals metrics into the matrix as acceptance criteria for speed, and the principles of the SEO Starter Guide for search readiness. Then "is it fast" stops being an impression and becomes a measurement.

Who runs testing, and what does acceptance testing cover?

Testing has two layers: the agency runs technical testing, and the client runs acceptance testing. Technical testing covers browser compatibility, mobile layout, form submission, and speed checks. Acceptance testing means the client walks through the site with their own eyes and asks "is this what the contract describes". Both layers, therefore, need their own row in the matrix.

Putting acceptance testing on the client side surprises some business owners. The question "I'm not technical, how can I test" is fair; still, acceptance testing is functional, not technical. Fill in the form and check that the email arrives. Tap the phone number and see whether a call opens, then walk through every page once on a phone. We prepared the full list in our website handover acceptance testing checklist.

Write duration and output into the testing row as well, for example "acceptance test, client, 3 business days, signed checklist". The signed checklist is the basis for launch approval; moreover, it prevents the post-launch argument "this bug was there before". Also note that defects found during testing are fixes, not revision rounds; put that in the notes section of the matrix.

Who handles the launch, and whose responsibility is launch day?

Launch, meaning moving the site to its live address, falls to the agency. However, domain pointing, SSL, and email continuity may require the client to talk to the hosting provider. So the launch row reads "agency produces, client provides access, both approve".

If you are redesigning an existing site, launch day needs extra care. Redirecting old addresses to new ones is the basic step for keeping rankings; Google's guide on how to move a site is the official source. Write the owner of content migration into the matrix too; we covered that topic in website redesign without losing SEO rankings.

Assign an owner for each of these launch day items.

  • DNS change: client grants access, agency applies it.
  • SSL certificate: hosting or agency installs it, agency verifies it.
  • Redirects: agency prepares and tests them.
  • Analytics and conversion tracking: agency sets it up, client grants account access.
  • Launch announcement: client announces by social media and email.

What to check in the first week after launch is collected in our website launch checklist.

How does the matrix cut the source of delays in advance?

Because the matrix puts an owner and a date on every row, it shows where a delay will be born before the project starts. If the dates of the client-owned rows pile up in the same weeks, you can see in advance that your team will not keep up. That foresight is the most practical way to prevent a delay instead of living through it. The check, moreover, takes five minutes on a calendar.

In practice, do this: mark every client row on the calendar and assign one person from your team to each. Is the person writing the copy at a trade show that week? Are the products ready for the photo shoot? Can accounting supply billing details? Thanks to the matrix, you ask these questions in week one, not month three. We examined the eight typical causes of delay and the fix for each in why web design projects run late. The matrix makes most of those causes visible in one table.

The same logic applies to the agency rows. Is there a gap between design delivery and development start? Are enough days reserved for testing? When you ask these questions in the proposal meeting, you also measure the agency's planning maturity.

What does a sample responsibility matrix look like?

The sample matrix below shows typical work items, owners, and due dates for a ten-page business website. It is an example calculation; the timing values are a starting range from field experience, not a guarantee. Add or remove rows for your own project.

Work itemProducesApprovesDueFormat
Brief and goalsClientBothWeek 1Brief document
SitemapAgencyClientWeek 1Page list
Access credentialsClientAgency verifiesWeek 1Secure share
Page copyClientClientWeek 2Single document
Logo and photosClientAgency checksWeek 2Vector and high resolution
DesignAgencyClientWeeks 3 and 4Desktop and mobile screens
DevelopmentAgencyAgency technical testWeeks 5 and 6Working staging site
Content entryAgencyClientWeek 6Populated pages
Acceptance testClientClientWeek 7Signed checklist
LaunchAgencyBothWeek 7Live site
Admin trainingAgencyClientAfter launchRecorded session

The "Format" column is missing from most matrices, yet we add it deliberately. The sentence "the copy was delivered" also covers copy arriving as ten separate chat messages, and the team cannot use that delivery. The format column closes that gap.

Who prepares the matrix, the agency or the client?

Preparing the matrix is the agency's responsibility, because the agency knows the process best. The client then reads it and says whether the client rows look realistic. So the agency drafts, and both sides approve the final version together. This split keeps the matrix true to real life, because dates written by the agency alone do not know your workload.

What if the agency does not offer a matrix? Take the table from this article, adapt it to your project, and ask in the proposal meeting "is this row yours or mine". The clarity of the answers reveals the agency's process experience. The matrix question is a practical addition to your proposal evaluation criteria, because it makes workload visible alongside price and time.

An experienced web design services team sends this table with the proposal anyway; in fact, it sets the dates of the client rows together with you. When you see that approach, the schedule risk of the project has already dropped considerably.

Whom should you assign from your own team?

Assign the client rows to the person who can actually do the work and has the time, not the person with the highest title. The general manager may sit in the approval row, but the copy row belongs to the salesperson who knows the subject best. A wrong assignment produces the same result as an ownerless row.

Ask three questions before assigning.

  • Does this person have another major commitment during the project weeks, for example a trade show, an audit, or vacation?
  • Can this person meet the delivery format; in other words, where will the vector logo or the high-resolution photos come from?
  • Does the decision authority sit with this person, or will they ask someone at every step?

Example scenario: in a clinic project the receptionist held the copy row, but she did not know the service details and asked the doctor about every paragraph. The copy, as a result, took four weeks. After they updated the matrix, with the doctor on the copy row and the receptionist on editing, the remaining pages finished in one week. In short, the matrix works when the right person sits in the right row; otherwise the table remains a pretty document.

How do you keep the matrix current during the project?

The matrix is not a document you write once and forget; a short weekly status note keeps it alive. Every week the agency reports in one message which rows closed and which client row is waiting. That message, in practice, works as an early warning before a delay is born.

Keeping it current, moreover, needs no heavy project tool. One shared table, three status colors, and a weekly email are enough. What matters is the rhythm, because a project that goes quiet for two weeks slips a month without anyone noticing. The agency writes the weekly note, but you reply briefly on your own rows, so both sides have looked at the calendar. The weekly note answers three questions.

  1. Which rows closed this week?
  2. Which rows are expected from whom next week?
  3. Is the schedule slipping, and if so, by how many days?

Keeping the matrix current pays off after launch as well. Move admin training, maintenance, and content updates into the post-launch section and keep using the same table. That way "who updates the site" is answered in week one, not on launch day.

Can the matrix be simplified for a small business?

For small business projects, you can reduce the matrix to five or ten rows and it still does the job. What matters is not the number of rows but that every row has one owner and one date. For a five-page site, rows for copy, images, access, approval, and testing are usually enough.

While simplifying, keep one principle: every item that stops the project when late stays in the matrix. Design does not finish without copy, launch does not happen without access, and likewise no stage closes without approval. Never delete those three rows, because they are exactly the tasks that halt a project. Also, even in a small project, put a person's name in the approval row; "I'll look at it" turns into "I'll look next week" during a busy stretch. Smaller items like the favicon or the social sharing image can merge into one row called "additional images".

To small business owners we say this: treat the matrix not as a burden but as a reminder that protects your own calendar. Your preparation list in business website pages checklist converts neatly into the client rows of the matrix; the two documents complete each other.

What goes wrong without a responsibility matrix?

In projects without a matrix, three problems repeat: ownerless work, duplicate work, and clashing expectations. Ownerless work, for example, is the copy nobody sends for three weeks. Duplicate work is the client and the agency both searching for the same stock photo. Clashing expectations is the sentence "I thought content entry was on your side".

These three problems feed each other. Ownerless copy runs late, so the agency moves to another project to avoid idle time. When the copy finally arrives the agency's calendar is full, and the project slips another month. This chain is one of the most frequent reasons projects stretch. The matrix breaks the chain at the first link, because the copy's owner and date are known in week one.

Example scenario: a service company without a matrix postponed its launch date twice, and each time the reason was "the photos weren't ready". For its second site the same company started with a matrix, wrote week two into the photo row, and planned the shoot in advance. Launch, as a result, happened on the first planned date. The difference was not the agency; it was a date written in a table.

What should you expect from the agency on the responsibility matrix?

What you should expect from the agency is a matrix that arrives with the proposal, with owners and dates written in. It also needs a format column and a weekly rhythm that keeps it updated. A good team does not impose the matrix on you; it sets the dates of the client rows together with you, around your own calendar. That behavior is a more reliable signal than any round count or price figure.

Talha Aslan and his team start every project with this table. Seeing the source of a delay in week one is easier than apologizing in month three. If you want to plan your project within that framework, our business website design page shows the steps of the process.

One last reminder: the responsibility matrix is not a document of distrust; it is a shared language that protects both sides. When you answer "who delivers what" in the first week, you protect the schedule, the budget, and your nerves at the same time.

Frequently Asked Questions

Who writes the content in a web design project?
Unless the contract says otherwise, the client writes the page copy; the agency supplies the structure, heading hierarchy, and character limits. You can buy copywriting as a separate service, but it must appear explicitly in the quote. In the matrix, write not only the owner of the content row but also the due date and format, because late copy is the most common reason projects overrun.
Who should prepare the responsibility matrix?
The agency drafts it, because the agency knows the process best; the client reads the client rows, says whether the dates are realistic, and both sides approve the final version together. If the agency offers no matrix, adapt the sample table from this article to your project and ask in the proposal meeting, row by row, whether each item is theirs or yours.
Why does the client run the acceptance test?
Acceptance testing is a functional check, not a technical one; you walk through the site with your own eyes to see whether it works as the contract describes. Filling in the form and confirming the email arrives, tapping the phone number to see a call open, and viewing every page on a phone is enough. The agency runs the technical test; both layers get separate rows.
When should I hand over access credentials?
Provide domain, hosting, current site admin, and analytics access in the first week of the project, because the agency cannot prepare the launch without them. If you are unsure who holds the credentials, investigate in week one so launch day holds no surprises. Never send passwords in an email body; use a password manager or a secure form, and narrow access after the project.
Is a matrix necessary for a small business project?
Yes, but you can simplify it to five or ten rows. Items that halt the project when late must stay: copy, images, access, approval, and testing. Small items such as the favicon or the social sharing image can merge into one row. What matters is one owner and one date per row, not the number of rows in the table.
How does the matrix prevent delays?
Because the matrix writes an owner and a date on every row, it shows where a delay will arise before the project starts. If the dates of the client rows overlap, you see in advance that your team cannot keep up that week, and you assign people early. The weekly status note also flags a waiting row early, so ownerless work, duplicate work, and clashing expectations never get started.
  • responsibility matrix
  • web design project
  • project management
  • content delivery
  • approval process
  • acceptance testing
  • web design
Share:
Talha Aslan

Google Partner digital marketing expert. Hands-on with SEO, Google Ads, web design and e-commerce projects since 2012; every post here comes from that experience.

Next project

Get a quote for your project.

Your brief goes straight to Talha Aslan and team: strategy led by Talha, delivery by an experienced team. We reply the same day and send the scope, timeline and price as a written quote within 1 business day.